Vendor Name: HP
Exam code: HP2-T26
Exam Name: Servicing HP BladeSystem Solutions
Click the link below to get full version
http://www.certifyguide.com/exam/HP2-T26/
Question: 1
|
Which feature is supported by
the zx2 chipset in the Integrity BL860c?
A. hot spare and hot-plug of
memory DIMMs
B. up to 512GB of memory (not
fully buffered DIMMs)
C. memory DIMM error
correction (chip sparing)
D. 512-bit, 800MHz (800 MT/s,
1600MHz data rate) memory bus
Answer: C
|
Question: 2
|
Which processor type is used
with the HP BL460c G6 Server Blade?
A. Dual-Core Intel® Itanium® Processor
B. Intel® Xeon® Processor
C. HP PA-RISC FSB, double data
rate
D. AMD Opteron processor
Answer: B
|
Question: 3
|
What is needed to connect a
Windows-based laptop to the c7000 or c3000 enclosure service port and
successfully communicate with the Onboard Administrator?
A. a laptop with the network
interface set to DHCP and a null modem cable
B. a laptop with the network
interface set to DHCP and a standard CAT5 patch cable
C. a laptop with the network
interface set to an address in the 192.168.1.x range and a CAT5 crossover cable
D. a laptop with the network
interface set to an address in the 192.168.1.x range and a standard CAT5 patch
cable
Answer: B
|
Question: 4
|
Which connectivity type is
supported to access Systems Management Architecture for the Server Hardware
(SMASH) Command Line Protocol? (Select three.)
A. serial
B. ftp
C. rcp
D. telnet
E. ssl
F. ssh
Answer: A, D, F
|
Question: 5
|
What is the maximum number of
SB1760c Tape Blades that can be installed in a c7000 blade enclosure?
A. 16
B. 8
C. 4
D. 2
Answer: B
|
Question: 6
|
How does a c7000 enclosure
retain air handling integrity when a server blade is removed?
A. The enclosure design uses
blank panels to prevent air loss.
B. A blanking panel causes the
air flow to reverse, allowing warmer air to escape.
C. The enclosure uses a
self-closing door to prevent air loss.
D. The fans increase in
revolutions per minute to increase air volume.
Answer: B
|
Question: 7
|
Which feature of the BL465c G7
allows the server to accommodate 16 DIMM slots and retain the half-height form
factor?
A. PCIe Gen 2 x8 mezzanine
expansion slots
B. AMD SR5690/SP5100 chipset
C. Hot Plug Drive Drawer
D. Smart Array P410i
Controller with 1GB FBWC
Answer: B
|
Question: 8
|
HOTSPOT
Click on the component that
provides remote enclosure management in c-Class enclosures.
Answer:
Question: 9
|
Which interconnect can be used
with the Fibre Channel over Ethernet (FCoE) capability of the new G7 Series of
c-Class blades?
A. HP 1/10Gb-F Virtual Connect
Ethernet
B. HP Virtual Connect Flex-10
10Gb Ethernet
C. Virtual Connect FlexFabric
D. HP ProCurve 6120G/XG
interconnect
E. HP Virtual Connect FC
Module
Answer: C
|
Question: 10
|
What happens when you turn the
enclosure UID to "On" on the Insight Display of a c7000 enclosure?
A. The rear enclosure UID LED
illuminates and the color of the Insight Display changes to blue.
B. The front enclosure UID LED
illuminates and the color of the Insight Display changes to blue.
C. The rear enclosure UID LED
illuminates and the color of the Insight Display changes to green.
D. The front enclosure UID LED
illuminates and the color of the Insight Display changes to green.
Answer: A
|
Question: 11
|
Which full-height device bays
are in Zone 3 of a c7000 enclosure?
A. 1 and 2
B. 3 and 4
C. 5 and 6
D. 7 and 8
Answer: C
|
Question: 12
|
Which HP BladeSystem component
is used for power allocation and control for all blades and interconnects?
A. Rack and Power Manager
B. Power Manager
C. Onboard Administrator
D. Insight Display
Answer: C
|
Question: 13
|
What is the maximum number of
c3000 enclosures that can be installed in a 42U rack?
A. 4
B. 5
C. 6
D. 7
Answer: D
|
Question: 14
|
Which HP c-Class server blades
take up two c3000 enclosure server bays? (Select two.)
A. BL860c
B. BL870c
C. BL685 G7
D. BL490 G6
E. BL2x220c G6
Answer: A, C
|
Question: 15
|
DRAG DROP
Place each server blade on its
recommended application type.
Answer:
Question: 16
|
HOTSPOT
Click on the SB600c All-in-One
Storage Blade in the graphic.
Answer:
|
Question: 17
|
Which HP blade comes with a
license for Microsoft Cluster Server (MSCS)?
A. BL490c
B. BL870c
C. X3800sb
D. xw2x220c
Answer: C
|
Question: 18
|
DRAG DROP
Place the preventive measure
steps in the correct order.
Answer:
Question: 19
|
Which utilities can be used to
scan for malware on a Windows server? (Choose two.)
A. Snort
B. Ad-Aware
C. Postfix
D. Microsoft Network Monitor
E. Spybot
Answer: B, C
|
Question: 20
|
When should a performance
baseline be captured?
A. after the initial
installation of the equipment, during normal daily operation
B. after the initial
installation of the equipment, during peak operating conditions
C. before and after each step
of the initial installation of the equipment
D. three times a day during
the first week following the initial installation of the equipment
Answer: A
|